PT Mitra Saruta Indonesia
Overview
HIJAU collaborated with PT Mitra Saruta Indonesia to install a 3,078 kWp rooftop solar PV system. As a company operating in the textile industry, it requires a stable energy supply to maintain optimal production quality. The solar PV system was installed at the company’s facility in Gresik City, East Java.
Project Details
HIJAU installed a 3,078 kWp rooftop solar PV system at PT Mitra Saruta Indonesia in Gresik, East Java. The project was completed in September 2025. With the rooftop solar PV system in place, the company is able to reduce its reliance on fossil fuels and transition to more environmentally friendly energy.
Challenges
HIJAU was able to carry out the construction and installation of the solar PV system smoothly and safely. The entire process proceeded according to the planned schedule. However, careful consideration was required in adjusting the placement of certain components to ensure that operations could run as expected.
Our Solution
HIJAU successfully adjusted the placement of system components to support smooth operational activities going forward. The HIJAU team conducted site surveys and multiple inspections to ensure the project was completed on time. HIJAU also supported the company in realizing its vision to transition to more affordable and environmentally friendly energy.
Result
The installation of a 3,078 kWp solar PV system at PT Mitra Saruta Indonesia was completed in September 2025. This installation successfully reduced carbon emissions by 92,960 tons, equivalent to planting 148,304 trees. PT Mitra Saruta Indonesia demonstrates its commitment to sustainability through the use of clean, environmentally friendly energy.
About Project
Status
COMPLETED
Location
Gresik
Capacity
3,078 kWp
Carbon Reduction
92,690 CO2