Solar Panel Installation at PT Setia Kawan Makmur Sejahtera

About the Project
Done On
Company:
PT Setia Kawan Makmur Sejahtera
Location:

HIJAU is currently working on a 1590 kWp rooftop solar power system (PLTS) installation project with PT Setia Kawan Makmur Sejahtera. As a company operating in the waste recycling sector, HIJAU is strongly committed to becoming an environmentally friendly business. The construction of this solar power plant serves as tangible evidence of its commitment to transitioning to eco-friendly and renewable energy.

Project Overview

A 1590 kWp solar panel installation is underway on the rooftop of PT Setia Kawan Makmur Sejahtera's factory, covering an area of approximately 1.5 hectares. The project involves the installation of 3,400 solar panels and is expected to be completed by 2025. Once operational, the solar power system will replace 5-10% of the electricity previously generated using fossil fuels with clean, renewable energy.

Challenges Faced

During this project, HIJAU encountered challenges such as the need for roof repairs prior to the installation of the solar panels. Therefore, effective collaboration and communication between PT SKMS, technicians, the factory, and the HIJAU team are crucial to ensure smooth progress and timely completion of the installation.

HIJAU's Solution

Before proceeding with the installation, the HIJAU team conducted site surveys and inspections, recommending roof repairs to ensure the long-term safety and durability of the solar panel system.

Results and Benefits

Once the solar panel installation is completed, the company will save 5-10% on electricity consumption and operational costs. This initiative will strengthen the company's Environmental, Social, and Governance (ESG) profile, enhance PT SKMS's reputation among investors, reduce operational expenses, and fulfill its commitment to environmental sustainability, further solidifying its position as an eco-friendly company.